Upcoming Road Work on Avent Ferry Rd. & Western Blvd., May 7-11

Below is a daily/nightly lane closure schedule for next week. Paving has been postponed until the end of May. Both sections of Western Boulevard require manhole/valve adjustments prior to paving. The section of Western Boulevard from I-440 to the Central Prison has curb ramp work that will be performed at night. Lane closures listed are weather dependent and could shift based on production. 

    Western (I-440 to Central Prison) – Nighttime curb ramp work (9 pm – 6 am)

    • Sunday, May 7
      • Right lane closure from I-440 to Central Prison
    • Monday, May 8
      • Right lane closure from I-440 to Central Prison
    • Tuesday, May 9
      • Right lane closure from I-440 to Central Prison
    • Wednesday, May 10
      • Right lane closure from I-440 to Central Prison
    • Thursday, May 11
      • Right lane closure from I-440 to Central Prison