Below is the nightly lane closure list for work performed next week along Western Boulevard between the Central Prison and I-440. Lane closures listed are weather dependent and could shift based on production.

Western (Central Prison to I-440) – NighttimePaving (8 pm6 am)

  • Sunday (July 2)
    • Left/Right lane closures from Avent Ferry to I-440
      • The contractor intends to pave full width and will shift lane closures mid-operation.
  • Monday (July 3)
    • Left/Right lane closures from Avent Ferry to I-440
      • The contractor intends to pave full width and will shift lane closures mid-operation.
  • Tuesday (July 4)
    • Left/Right lane closures from Avent Ferry to I-440
      • The contractor intends to pave full width and will shift lane closures mid-operation.
  • Wednesday (July 5)
    • Left/Right lane closures from Avent Ferry to I-440
      • The contractor intends to pave full width and will shift lane closures mid-operation.
  • Thursday (July 6)
    • Left/Right lane closures from Avent Ferry to I-440
      • The contractor intends to pave full width and will shift lane closures mid-operation.

Western (I-440 to Central Prison) – Curb Ramp Work and Utility Adjustments (8 pm6 am)

  • Sunday (July 2)
    • Right lane closure from I-440 to Avent Ferry.
  • Monday (July 3)
    • Right lane closure from I-440 to Avent Ferry.
  • Tuesday (July 4)
    • Right lane closure from I-440 to Avent Ferry.
  • Wednesday (July 5)
    • Right lane closure from I-440 to Avent Ferry.
  • Thursday (July 6)