The paving is complete. The remaining items include signal loop installation in the pavement, curb ramp construction, roadway final striping, and shoulder grading. Nightly lane closures for this week include:
Western (I-440 to Central Prison) – Curb Ramp and Inductive Loop Work (8 pm – 6 am)
- Sunday (September 10)
- Left and right lane closures to install inductive loop wire for signal loops along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound Western Boulevard.
- Monday (September 11)
- Left and right lane closures to install inductive loop wire for signal loops along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound Western Boulevard.
- Tuesday (September 12)
- Left and right lane closures to install inductive loop wire for signal loops along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound Western Boulevard.
- Wednesday (September 13)
- Left and right lane closures to install inductive loop wire for signal loops along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound Western Boulevard.
- Thursday (September 14)
- Left and right lane closures to install inductive loop wire for signal loops along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound Western Boulevard.