The paving is complete. The remaining items include signal loop installation in the pavement, curb ramp construction, and roadway final striping. Nightly lane closures for this week include:
Western (I-440 to Central Prison) – Curb Ramps, utility adjustments, and inductive loop installation (8 pm – 6 am)
- Sunday (October 15)
- Left and right lane closures to install inductive loop wire for signal loops and roadway striping along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound and westbound Western Boulevard.
- Monday (October 16)
- Left and right lane closures to install inductive loop wire for signal loops and roadway striping along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound and westbound Western Boulevard.
- Tuesday (October 17)
- Left and right lane closures to install inductive loop wire for signal loops and roadway striping along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound and westbound Western Boulevard.
- Wednesday (October 18)
- Left and right lane closures to install inductive loop wire for signal loops and roadway striping along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound and westbound Western Boulevard.
- Thursday (October 19)
- Left and right lane closures to install inductive loop wire for signal loops and roadway striping along eastbound and westbound Western Boulevard.
- Right lane closures for curb ramp work along eastbound and westbound Western Boulevard.