Power Forward Traffic Impacts on Dan Allen Drive
Please see the note below from Construction Management about the current traffic impacts due to the Power Forward Project.
Dan Allen Drive under the railroad bridge was closed entirely yesterday due to unforeseen underground conditions related to the Dan Allen Domestic Waterline project. It will now remain closed as part of the Power Forward work. Power Forward work will also be closing Katharine Stinson Drive between Bureau of Mines and Broughton Hall
The target dates for the closure of Dan Allen Drive under the railroad bridge are July 19 to Sept. 27, 2024. It will be reopened temporarily during move-in week, Aug. 12-18, and closed again until approximately Sept. 27, 2024. The target dates for the closure of Katherine Stinson Drive between Bureau of Mines/Broughton is July 22 to Aug. 14, 2024. These dates are subject to change due to weather or other unforeseen issues.
Please see the graphics on pages 6 and 7 here. These graphics can also be found on the Power Forward Web Page by clicking on the “MAP OF CURRENT TRAFFIC IMPACTS.”
Moving forward, I would encourage you to visit the webpage periodically for any updates to the work schedule and associated closures. These graphics are updated by the project team at a minimum weekly, or sooner if there are any significant changes to the dates due to weather or other unforeseen issues.
If you have any questions or concerns about this information, please do not hesitate to contact me. Calling me on my mobile is the best course of action if you have a time-sensitive request.
Thank you for your continued patience with the project!Best Regards,