Upcoming Road Work on Avent Ferry Rd. & Western Blvd., May 14-18

Below is a daily/nightly lane closure schedule for next week. Paving has been postponed until the end of May. Both sections of Western Boulevard require manhole/valve adjustments prior to paving. The section of Western Boulevard from I-440 to the Central Prison has curb ramp work that will be performed at night. Lane closures listed are weather dependent and could shift based on production. 

Western (I-440 to Central Prison) – Nighttime curb ramp work (9 pm – 6 am)

  • Sunday, May 14
    • Right lane closure from Central Prison to I-440
  • Monday, May 15
    • Right lane closure from Central Prison to I-440
  • Tuesday, May 16
    • Right lane closure from Central Prison to I-440
  • Wednesday, May 17
    • Right lane closure from Central Prison to I-440
  • Thursday, May 18
    • Right lane closure from Central Prison to I-440